Why we accept all Major Credit Cards, Apple Pay and Android Pay

At Icelabz we like talking to our customers and one of the pain points that we see our customers face every day is financing their project and paying for them.

Especially at the early stage of your projects; where you are still trying to get your architect to complete their proposed drawings for planning applications and get tenders in from contractors.

So we’ve made it easier for you to pay on credit.

How we’ve done it

 

We have teamed up with Stripe so that we can provide you with the best rates without charging you transaction fees. (We don’t pass on the charges to you)

Stripe allows our customers to use their credit card which includes American Express and other major credit cards that offer cash back incentives.

This is great for our customers as this can potentially save them cost and manage their cash flow at early stages of their project.

List of ways you can pay

In addition to paying with your credit card you can also pay using:

  • Apple Pay
  • Android Pay
  • Direct Debit

This helps you transact with us faster, get things done on the go without logging into your bank account and setting up a new recipient – which can take 10-15min

Design and Build Risk I’ve found as a Quantity Surveyor

Some of you may have noticed that my background is in Quantity Surveying and specialized in commercial issues and disputes.

Even though I don’t provide this service, I still have discussions with architects and friends in the industry regarding their projects.

One story ticked me off as to how a contractor was swindling a poor homeowner.

Some background on the project

The project is based in Central London, and it is for the renovation of a £5million 2 storey flat. I wasn’t given the address, but I was given a brief of the issue and had to review the proposal from the contractor.

Some high-level details:

 

  • The main architect had a good relationship with the contractor
  • My friend was working with a different interior designer for the design
  • The price came around £1.9m for the renovation
  • The procurement route was traditional as some of the works had specialist (I’ll explain this in a future post)
  • Some of the M&E design was not done yet so it was passed on to the contractor as a contractor’s design portion which they put in as a provisional sum.

Issues I found when looking at the price

  • The price was hard to understand as it was not using any standard method of measurement. That to me is a big red flag.
  • As some of the design for the Mechanical and & Electrical was not complete, you would expect some provisional sum for it. However, it was not defined. Another red flag.
  • The listed 10% of the contract value as a Provisional sum but when I totaled up the additional comments throughout their pricing sheet, it came up to 45%. All of which were not defined. Another red flag. Most of the comments were related to structural design not complete. I was a bit confused as the structural engineer already provided the drawings for all of the necessary items.

I flagged these to my mate.

Why it was a problem

 

As a homeowner, you won’t be aware what a provisional sum is, and you could expect a reasonable amount on certain projects but! not 45% of the contract value.

You can learn more about the provisional sum on this post. But in brief…

having a provisional sum in the contract means that

  1. It’s not part of the contract to be delivered by the contractor, and you need to formerly instruct them
  2. the price will definitely change because the provisional sum has not been defined. Even the NEC contract
  3. As the client, you are taking the risk of the provisional sum activity
  4. You will need to pay more if the provisional sum is instructed as it will delay the program of works. This goes back to point 1. As the item of work is not part of your contract.

Need more information about provisional sum? Read this

… or still confused?

think of provisional sum as an item on a quote that is just a really rough estimate as the person who gave you the quote doesn’t know how much it will cost because he doesn’t enough information. So he took an educated (not really) guess of how much it costs.

Problem is that you’ll be taking a lot of risk on the item he couldn’t quote properly.

A good way to avoid this is to get

  • a complete design of the property
  • a Quantity Surveyor to create a bill of quantity for you
  • to instruct the contractor to price it against a standard method of measurement such as the NRM 2 (New Rules of Measurement 2). This can potentially help consultants later in your project understand what has been priced exactly.
  • or get the contractor to go on a design and build contract where they take the risk of the incomplete design.

Spam blocking for our enquiry page

We have recently been swamped with SPAM bots on our website and specifically our client’s measured survey portal.

We have now included reCaptcha from Google and we have added additional checks which will force certain user submission to be parked until they pass through the recaptcha checks. Our mail system and database was overwhelmed with the number of SPAM.

Since we’ve implemented the update we’ve seen an immediate stop to the SPAM submissions.

I will continue to monitor the submissions and add additional rules to block these submissions.

http://gty.im/538806241

What is an Architectural Survey?

What is an Architectural Survey?

An Architectural Survey is a survey to capture the position and measurement of all structural and aesthetic feature of the property. It is also called a Measured Building Survey, or Measured Survey of Building.

There are different types of measured surveys; building, land and utilities.

The architectural survey focuses on the building’s features. They are usually represented on 2D drawings to allow your architect or other professionals to use it to produce proposed plans, reports, or calculations.

The architectural survey can include different types of plans. Here is a list of the plans that forms part of the survey:

  1. Floor plans
  2. Elevation plans
  3. Section plans
  4. Roof plans
  5. Ceiling plans
  6. Internal Elevation Plans

Take a look at this article for more information on what is included in a measured building survey.

The architectural survey can also include the external of the property. This is a Topographical Survey.

If you are confused about the terminology and what types of surveys there are read this guide on the different types of measured surveys.

 

Exit mobile version